Projet de loi portant diverses dispositions relatives au secteur nucléaire

Tabled on October 14, 2026

What changes

The bill would extend fast-track planning and construction rules, which were previously created for new nuclear reactors, to fuel cycle facilities such as fuel treatment and storage plants. It would also allow nuclear operators to derogate from certain general building codes for safety reasons, and permit them to delegate the oversight of external contractors to subsidiary companies within their group.

Mainly concerns: Nuclear facility operators, External contractors in nuclear sector, Nuclear safety authority (ASNR)

The main articles

  • art. 1 — Extends fast-track administrative procedures to fuel cycle facilities and deep geological repositories, allowing specific construction works to begin after the public inquiry closes but before the final creation decree is issued.
  • art. 2 — Allows nuclear operators to derogate from specific rules in the construction and housing code if complying with them would increase nuclear safety risks or prove technically impossible.
  • art. 3 — Permits nuclear operators to delegate the surveillance of external contractors to subsidiary companies, provided the nuclear safety authority grants prior authorization.

The detailed explanation

This is an ordinary bill amending the Environment Code and the 2023 law on accelerating nuclear procedures (commonly known as the "ADN" law).

Article 1 broadens the scope of the accelerated procedures created by the 2023 ADN law, initially aimed at new nuclear reactors, to include fuel cycle facilities (such as those enriching or reprocessing fuel) and deep geological radioactive waste repositories.

Concretely, Article 1 would allow operators to begin preparatory earthworks as soon as environmental authorization is granted, and to start constructing buildings and foundations immediately after the public inquiry concludes, without waiting for the final creation authorization decree. Article 2 would permit operators to seek exemptions from certain provisions of the Construction and Housing Code if compliance would jeopardize nuclear safety or is technically impossible. Article 3 would enable operators to delegate the oversight of external contractors to their own subsidiaries or group companies.

The bill leaves several matters to executive decree, notably the conditions under which an operator may delegate contractor surveillance (Article 3). It also empowers the minister in charge of nuclear safety to apply further exemptions to specific fuel cycle projects by order (arrêté) upon request, stipulating that a failure to reply within six months counts as a rejection (Article 1). No habilitations to legislate by ordonnance are granted.

Safeguards are attached to these new flexibilities. Works started before the final creation decree are undertaken at the operator's own risk and expense, and the structures must be capable of being modified to meet the final decree's requirements. The nuclear safety authority (ASNR) retains the power to impose provisional protective measures during early construction (Article 1). Furthermore, delegating contractor surveillance requires prior ASNR authorization, and the text expressly states that the primary operator retains full responsibility and control (Article 3).

The bill does not defer its own entry into force. The fast-track procedures for fuel cycle facilities would only apply to creation requests filed within 20 years of the promulgation of the text.

The bill adjusts the sequencing of environmental review processes relative to the start of physical works, ensuring the public is informed during the inquiry that early construction may occur, while shifting the financial risk entirely to the operators.

What the Government says, and what the text does

The exposé des motifs argues that extending accelerated procedures to fuel cycle facilities and allowing building code derogations will ensure energy independence and prioritize nuclear safety. The articles accurately carry out these aims by amending the 2023 law to include these facilities and establishing specific derogation mechanisms. The text aligns closely with the stated objectives.

Does it respect the rule of law?

Ten principles, each strengthened (▲), unchanged (·) or weakened (▼), with the articles concerned.

  • The law itself decides the essentialsThe bill does not engage this principle.
  • Clear, non-retroactive rules (art. 1, art. 2)Article 2 resolves potential conflicts of norms by formally allowing nuclear authorizations to derogate from general building codes when compliance would harm nuclear safety or be technically impossible. Article 1 clarifies the legal status of early construction works by explicitly permitting them before the final decree is issued, removing ambiguity about what can be legally built at the operator's own risk.
  • Administrative powers are bounded (art. 3)By allowing operators to delegate the oversight of contractors to subsidiary companies, Article 3 mitigates the risk of diluted accountability by expressly forbidding sub-delegation and stating that the primary operator retains full responsibility, direction, and control over the surveillance. It also requires prior authorization from the independent nuclear safety authority.
  • Equality before the lawThe bill does not engage this principle.
  • Access to a judgeThe bill does not engage this principle.
  • Rights and freedomsThe bill does not engage this principle.
  • Proportionate measuresThe bill does not engage this principle.
  • Review or end date planned (art. 1)Article 1 imposes a strict time limit on its scope, restricting the use of the new fast-track procedures for fuel cycle facilities to those projects for which an authorization request is filed within twenty years of the bill's promulgation.
  • Room left to local authoritiesThe bill does not engage this principle.
  • Openness of public actionThe bill does not engage this principle.

What the text leaves open

  • The specific conditions and modalities under which a nuclear operator can delegate the surveillance of external contractors remain to be settled by a Conseil d'État decree.

From the official file

The file on Légifrance →

This page is generated automatically by AI (Google Gemini) from the official text. It has not been reviewed by a jurist and may contain errors. It is not legal advice: only the Journal officiel is authoritative.

Support LegiCivica

LegiCivica is free, ad-free and independent. Your donations keep LegiCivica free for everyone and fund what comes next.

Make a donation on Ko-fi

Opens ko-fi.com in a new tab.